1069 - 2386

The Road to Recovery

The case Conarken Group Limited, Farrell Transport limited v Network Rail Infrastructure Limited [2011] EWCA Civ 644

The issue

Vehicles frequently damage railway bridges, crossings and other rail infrastructure, which often causes disruption to rail services. Responsibility for the rail infrastructure rests with Network Rail Infrastructure Limited, who are contractually obliged to pay compensation to Train Operating Companies (TOCs) when a line is closed.

In the first case, the judge awarded damages to Network Rail, including recovery of the full compensation payments it had made to TOCs. The decision was appealed, and the judgement of the Court of Appeal was made on 27 May this year. Having briefly covered this in the last issue of SMIB, we now look at the case in more detail.
 
The facts

The case involved two separate incidents, both of which resulted in the closure of a railway line. The first involved a vehicle operated by Conarken, and resulted in a line being closed for five days. The second incident, involving a Farrell vehicle, saw the East Coast Main Line closed for five hours.

In both cases, primary liability was accepted. In addition to the cost of repairs, which were relatively minor, Network Rail had paid substantial compensation to the TOCs in accordance with its contractual obligations. The calculation of compensation was complex, including factors such as the relative importance of the line, the length of delay and the impact upon future customer usage and confidence.

The issue at appeal was whether Network Rail's liability to pay the compensation was within the scope of the appellants' duty and, if so, whether they had to pay the contractually agreed sums.

The defenders disputed the claims on three grounds. Firstly, they argued that they did not owe a duty of care to Network Rail to prevent them suffering an economic loss. Second, that the loss was too remote to be recoverable. Third, that the compensation included a penal element and could not therefore be considered truly consequential upon physical damage.

At appeal, the court examined whether the law of remoteness restricted the amount that a claimant such as Network Rail can recover where contractual liabilities arise. There was lengthy discussion regarding the contractual payments and whether they are binding for the purpose of a negligence action. Particularly controversial was the inclusion of future loss of revenue within the contractual payment, although importantly the defenders had accepted that the contractual payments represented the best assessment in financial terms.

The decision

The appeal was dismissed and full recovery was allowed. Liability to compensate was a direct consequence of the negligence. The court took care to emphasise that the existence of a contractual obligation did not guarantee recovery. The relevant principles were summarised in four propositions:

1. Economic loss which flows directly and foreseeably from physical damage to property may be recoverable. Detailed knowledge of the claimant's business is not required so long as the general nature of the loss is foreseeable.
2. One of the recognised categories of recoverable economic loss is loss of income following damage to revenue generating property.

3. Loss of future business as a result of damage to property lies on the outer fringe of recoverability. Recovery will depend upon the circumstances of the case and the relationship between the parties.

4. When assessing damages, the court will seek to arrive at an assessment which is fair and reasonable.


Douglas Brodie

This is an important cases for insurers. A relatively short closure of the East Coast Main Line resulted in a very substantial award. Vehicle damage to rail infrastructure is a frequent problem, so the potential exposure is substantial.

The basic principle of pure economic loss remains in place: had the TOCs claimed direct against the negligent party they would have failed on the grounds that none of their property was damaged and their claim was purely economic. However, in future cases with similar circumstances, the existence of a contract giving rise to financial liability is likely to result in a requirement to pay damages. It is not clear how the boundaries of recoverable loss will be determined.

The difficult question is how to determine what is fair and reasonable in the face of frequently complex contractual arrangements? In Conarken, the compensation was accepted as a reasonable assessment of the TOC losses. Lord Justice Pill observed that the agreement was "responsibly drafted with a view to achieving a fair result," and public interest was also a relevant consideration.

Lord Moore-Bick commented: "That some financial loss would be likely to result from a suspension of services, whoever was operating them is, I think, obvious." It may be that in future similar cases, provided the contractual liabilities can been seen as a fair assessment of loss, pursuers in negligence will not be hindered by the law of remoteness.


 

Subscribe to our news feeds

Keep up-to-date with all of our publications, legal updates, firm news and events.

Firm NewsLegal UpdatesSMIBEvents